Contractors wishing to conduct asbestos abatement activities on any Michigan State University (MSU) project must first be prequalified by the Department of Environmental Health and Safety (EHS). Contractors selected for prequalification will be approved every calendar year and will need to reapply in September for the next calendar year. Successful prequalification does not specifically guarantee work with MSU.

Anticipated Prequalification Schedule

Prequalification Schedule
Description Date
Application Release September 18, 2023
Last Postmark Accepted November 3, 2023
Contractor Prequalification Notification December 15, 2023
Prequalification Period January 1 - December 31, 2024

For contractors pre-approved for the previous 3 years, submit the Modified Abatement Prequalification Application (PDF).  For all other contractors, submit the Abatement Prequalification Application (PDF).

Prequalification Submission

Submit an electronic copy of your completed application via flash drive (physical media) or a link to Dropbox or Google drive type shared file service. If you choose to submit paper copies of the completed application please send three (3) copies. Packages must not be postmarked or delivered later than November 3, 2023. Late and facsimile submissions will not be considered.

Mail completed applications to: Gary C. Bosh - boshgary@msu.edu

Gary C. Bosh, Environmental Technologist
Department of Environmental Health and Safety
Michigan State University
4000 Collins Rd. Room B-20
Lansing, MI 48910

OR completed applications labeled “Abatement Prequalification, Attn: Gary C. Bosh, Environmental Technologist” may also be delivered in person between 8am and 4:30pm to the EHS Main Office at:

4000 Collins Rd. Room B-20
Lansing, MI 48910

MSU will determine the final list of prequalified abatement contractors. MSU is not responsible for any expenses incurred in the preparation of this prequalification application nor does MSU assume any contractual obligation by issuing this application. MSU may elect to interview contractors or request additional information. MSU reserves the right to reject any and all submittals either in whole or in part and to waive any irregularities. Please be aware that submittals may be subject to a Freedom of Information Act (FOIA) records request pursuant to MCL Sections 15.231 to 15.246.

MSU reserves the right to waive prequalification requirements for abatement contractors on a limited case by case basis. A waiver of prequalification must be in writing from MSU EHS and will be specific to a single project. MSU also reserves the right to remove contractors from the prequalified list for noncompliance with the applicable asbestos regulations, a project-specific asbestos specification, or the MSU asbestos management plan.

Successful applicants will be listed here by December 15, 2023.